Scope of work
The level crossing at Skye Road, Frankston on the Frankston Line was identified for removal as part of the Level Crossing Removal Project to remove 50 of Victoria’s most dangerous and congested level crossings. As part of these works, Civil Infrastructure Group was contracted to construct the substructure for a new rail bridge.